Musk's Colossus 2 Is Racing to 1.2 Million GPUs — and Power Is the Real Bottleneck
November 2, 2026 · 5 min read
Elon Musk disclosed on November 1 that the four buildings of Colossus 2 in Memphis already hold about 860,000 Nvidia GB300 chips, with a year-end target of roughly 1.2 million Blackwell GPUs. The training building, Gun Range, is scheduled to come online at the end of November, and the inference building, Spam, follows in December. And here is the number that reframes the whole project: based on HPE rack specifications, 1.2 million cards would draw about 2.2GW in rack power alone (via Converge Digest).
Here is the analysis, plainly marked as such: the headline number is the GPU count, but the real story is the power figure tucked underneath it. Buying 1.2 million chips is a procurement problem, and procurement problems can be solved with money and purchase orders. Delivering 2.2GW of electricity to one site is an infrastructure problem, and infrastructure problems answer to grids, permits, substations and construction crews, none of which move at the speed of a purchase order. The race to 1.2 million cards is, underneath, a race to plug them in.
What 1.2 million cards actually means
Start with the scale, because it is easy to read past it. About 860,000 GB300s are already installed across four buildings, which means the project is not a plan on paper but a mostly built machine. Reaching roughly 1.2 million by year-end means adding about 340,000 more cards in roughly two months, a pace that would strain any supply chain on its own. The two named buildings also show the site is splitting into two jobs: Gun Range trains models, Spam serves them. That division matters because training and inference stress a data center differently — training wants huge, synchronized bursts of compute, while inference wants steady, low-latency capacity that is always on. Colossus 2 is not just getting bigger; it is getting organized into a full pipeline, from training a model to answering users with it.
Why power, not chips, is the bottleneck
The 2.2GW figure deserves a second look, because it is deliberately narrow: it covers rack power only, the electricity the GPU racks themselves draw. Cooling, networking, storage and the rest of the building sit on top of that, so the site's total draw will be higher still. Two gigawatts is the scale of a large power station's output, or roughly what a mid-sized city consumes, and it has to arrive through grid connections that take years to plan and build. Chips can be manufactured faster than substations can be permitted. That is why the power number, not the GPU count, is the honest measure of how fast this build-out can actually go: every card that arrives without a matching watt is a very expensive paperweight, and the grid does not care how ambitious the roadmap is.
What to watch before year-end
Three dates will test whether this roadmap holds. First, does Gun Range actually come online at the end of November, on the schedule Musk gave. Second, does Spam follow in December, giving the site its inference half. Third, and most revealing, does the 1.2 million card target get met, or does it slip quietly into next year — and if it slips, is the stated reason chips, construction, or power. A slip blamed on power would confirm the bottleneck thesis in the most concrete way possible. A slip blamed on chip supply would tell a different story, about Nvidia's output rather than the grid. Either way, the year-end count is less interesting than the reason given for any gap, because that reason names the next constraint the whole industry will have to solve.
One sentence to take away
Colossus 2 already holds about 860,000 GB300s and aims for roughly 1.2 million Blackwell GPUs by year-end, with Gun Range due in late November and Spam in December — but at about 2.2GW of rack power alone, electricity, not silicon, is what will decide how fast AI infrastructure can actually grow.